$18 million electricity projects in Basra – official

BASRA / IraqiNews.com: U.S. reconstruction team has started implementing electricity projects in Basra with a total cost of $18.8 million to save energy and reduce the power cut, a general manager of Basra electricity said on Friday. “The projects include extending 14 cables with11kV power at a cost of $5.4 million to save power through the national net,” Sabah Abdulwahed told IraqiNews.com news agency, noting that seven cables have been so far finalized in al-Jubiela, al-Jomhouriya, al-Janieniya, al-Maaqal, Fao, al-Sharieh and al-Arab regions. “The main cable is being extended with a capacity of 132kV from Bab al-Zubair until the Basra electricity stations with a total cost of $8 million,” he added, noting that the project will complete next month. “There are three projects to fix the electricity system in the southern province,” he continued, pointing out that the project costs $1.2 million. Basra is 590 km south of Baghdad. SH (P) 1